The project was co-financed by the European Union from the European Fund for Regional Development
Project title (operation) of the beneficiary /partner in the project:
“Construction of photovoltaic power plant Plastform for the needs of the production plant ”
Operational Programme: Competitiveness and Cohesion 2014-2020
Short description of the project (operation):
On 20th of November in 2017., the company Plastform d.o.o. started with the implementation of the project of construction of photovoltaic power plant Plastform for its own needs. Within the project, the construction of a photovoltaic power plant Plastform for self-consumption power of 87.7 kW, consisting of 422 modules with a power of 270 W, is planned. The construction of a photovoltaic power plant will reduce the consumption of electricity from conventional sources, so that energy for the needs of the production plant will be obtained from RES.
Objectives and expected results of the project (operation):
Energy consumption from conventional sources per year is 238,080 kWh. The total production of the photovoltaic power plant will be 115,960 kWh. Energy savings will be 48.71%, and the CO2 reduction will be 27.23 t. Plastform’s share of renewable energy in total energy will be 48.71%.
The total value of the project and the part co-financed by the EU (in HRK):
The total value of the project is HRK 1,049,277.71.
Grants participate in the financing of the project in the amount of HRK 724,006.97
The project implementation period is from 20 November 2017 to 31 December 2020.
Contact person for more information:
Technical Director: Ante Topić
Phone: +385 99 6086 559
e-mail: topic@plastform.hr